Construction of 132 kV overhead power line Zirc North-Litér, Phase IV
Construction of a 132 kV overhead power line Zirc North-Litér: Execution of foundation work, pole erection and assembly, and wiring and underground cable laying for a new single-system 132 kV overhead power line between the substation Zirc (to be rebuilt) and the existing substation Litér. The route runs parallel to the existing 400 kV overhead power line and has a total length of approx. 22.3 km, of which approx. 21.2 km is overhead line. Connection to the Litér substation is via approx. 1 km NAF cable. The work involves a total of 91 poles of various types. The completion deadline for the overall service is 140 working days from contract signing, with the period from December 15 to January 15 excluded due to weather conditions. Procurement of materials and equipment not provided by the client is the contractor's responsibility.
CONTRACTING AUTHORITY
Name
E.ON Észak-dunántúli Áramhálózati Zrt.
City
Győr
Country
HU
CLASSIFICATION
Procedure Type
Open Procedure
Contract Type
Works
Main CPV
45000000, Construction work.
Other CPV
45100000, Site preparation work.
45223100, Assembly of metal structures.
45231400, Construction work for electricity power lines.
45223500, Reinforced-concrete structures.
45223800, Assembly and erection of prefabricated structures.
45231600, Construction work for communication lines.
45100000, Site preparation work.
45223100, Assembly of metal structures.
45231400, Construction work for electricity power lines.
45223500, Reinforced-concrete structures.
45223800, Assembly and erection of prefabricated structures.
45231600, Construction work for communication lines.
45100000, Site preparation work.
45223100, Assembly of metal structures.
45231400, Construction work for electricity power lines.
45223500, Reinforced-concrete structures.
45223800, Assembly and erection of prefabricated structures.
45231600, Construction work for communication lines.
LOTS (3)
Gründungsarbeiten für 132 kV Freileitung Zirc Nord-Litér
Maststellung und -montage für 132 kV Freileitung Zirc Nord-Litér
Verkabelung und Erdkabelverlegung für 132 kV Freileitung Zirc Nord-Litér
ADDITIONAL DETAILS
EU Funded
Yes
Suitable for SMEs
Yes
Electronic Submission
Required
Legal Basis
32014L0025
DEADLINES & TIMELINE
Submission Deadline
32 days remaining(LOT-0001)