Expansion of E&I Technology for the Graz Wastewater Treatment Plant
We are expanding and adapting the electrical and E&I installation at the Graz wastewater treatment plant to ensure power supply for new and renovated sections. Work is scheduled to begin around July 1, 2026, and conclude by December 14, 2028.
CONTRACTING AUTHORITY
Name
HOLDING GRAZ - KOMMUNALE DIENSTLEISTUNGEN GMBH
City
Graz
Country
AT
CLASSIFICATION
Procedure Type
Open Procedure
Contract Type
Works
Main CPV
45310000, Electrical installation work.
Other CPV
45315500, Medium-voltage installation work.
45317200, Electrical installation work of transformers.
45314300, Installation of cable infrastructure.
48921000, Automation system.
ADDITIONAL DETAILS
Electronic Submission
Required
Legal Basis
32014L0025
DEADLINES & TIMELINE
Submission Deadline
No deadline specified
(LOT-0001)
Published