Building automation for all building sections of a new construction, planned for a start in late October 2026: automation equipment, control cabinets, automation focal points, automation management, cables, lines and installation systems, data transmission networks. Execution for building section 3: 40 days (5-day week) starting 07.12.2026; for building section 4: 10 days (5-day week) starting 21.01.2027. Deviations from the planned start will be communicated at least 4 weeks in advance.
CONTRACTING AUTHORITY
CLASSIFICATION
Procedure Type
Open Procedure
Contract Type
Works
Main CPV
45331000, Heating, ventilation and air-conditioning installation work.
Other CPV
45311200, Electrical fitting work.
ADDITIONAL DETAILS
EU Funded
Yes
Suitable for SMEs
Yes
Electronic Submission
Required
Legal Basis
32014L0024
DEADLINES & TIMELINE
Submission Deadline
22 days remaining(LOT-0001)