Hazardous Material Remediation and High-Voltage Supply Renewal for DLR Göttingen
Hazardous material remediation according to TRGS 519 and TRGS 521: removal of asbestos-containing flooring and dismantling of insulation on existing district heating lines, 120 m² OSB dust protection wall, 120 m² foil-batten dust protection wall, 180 m² magnesia flooring including floor covering, 120 linear meters of KMF/diatomaceous earth pipe insulation, disposal of hazardous materials. Execution period approximately October 2026 to November 2026.
CONTRACTING AUTHORITY
Name
Deutsches Zentrum für Luft- und Raumfahrt e. V.
City
Braunschweig
Country
DE
CLASSIFICATION
Procedure Type
Open Procedure
Contract Type
Works
Main CPV
45262660, Asbestos-removal work.
ADDITIONAL DETAILS
EU Funded
Yes
Suitable for SMEs
No
Electronic Submission
Required
Legal Basis
32014L0024
DEADLINES & TIMELINE
Submission Deadline
29 days remaining(LOT-0000)