Management and Investor Supervision for Railway Line and Station at Modlin Airport

Management and investor supervision for the realization of the investment project for the construction of a railway section from Modlin to Mazowiecki Port Lotniczy (MPL) Warszawa/Modlin and the Mazowiecki Port Lotniczy (MPL) Warszawa/Modlin railway station: This includes, as basic scope, the management, supervision, and control of construction contracts, functioning as Engineer according to the Agreement and Construction Contract, material and financial management including settlement, monitoring, and reporting, technical management with investor supervision duties, coordination of the construction contract, and environmental and natural supervision (control of construction process impact on surface and groundwater, noise, air, soil, waste management, green areas) according to environmental decisions and administrative requirements. An option for extending the investor supervision service by a maximum of 12 months is included.

CONTRACTING AUTHORITY

Name

PKP Polskie Linie Kolejowe S.A.

City

Warszawa

Country

PL

CLASSIFICATION

Procedure Type

Open Procedure

Contract Type

Services

Main CPV

71520000, Construction supervision services.

Other CPV

71247000, Supervision of building work.

71521000, Construction-site supervision services.

ADDITIONAL DETAILS

Electronic Submission

Required

Legal Basis

32014L0025

DEADLINES & TIMELINE

Submission Deadline

46 days remaining

(LOT-0001)

Published

TENDER DOCUMENTS

46 days remaining

Similar Tenders

Explore CPV 71

Construction works for railway access to Lubiatowo – Kopalino Nuclear Power Plant, Wejherowo – Choczewo section

Construction works for railway access to the Lubiatowo – Kopalino Nuclear Power Plant, Wejherowo – Choczewo section: includes the execution of works in the areas of track surface and subgrade, drainage, railway traffic control devices (srk), telecommunication devices and systems, traction network with power supply, electrical power devices and systems up to 1 kV, engineering structures, platforms and building structures, crossings and level crossings, sanitary works, and geology. Also included are construction works for environmental protection facilities and the preparation of as-built documentation, comprising technical regulations (based on Ir-3 Instruction), geodetic as-built documentation (line picketage and longitudinal profile, acceptance protocols for track axis adjustment marks, numerical situational-height map with geodetic as-built inventory), documentation for the establishment and measurement of the basic and special railway geodetic control networks, and new schemes for traffic posts and expedition points. Detailed information is provided in the Technical Specifications for the Execution and Acceptance of Construction Works (STWIORB) and the descriptive and drawing part of the Project Documentation (Volume III SWZ), as well as in the Bill of Quantities (Volume IV SWZ).

PKP Polskie Linie Kolejowe S.A.

·Warszawa
Deadline:July 28, 2026

Expansion of the Training Center for Railway Protection Guard and Dog Breeding and Training in Zbąszyn

Design and execution of construction works for the expansion of the Training Center for Railway Protection Guard and Dog Breeding and Training in Zbąszyn: Preparation of all project documentation (building, technical, executive, and workshop documentation) including obtaining all necessary administrative decisions and permits; execution of all construction works according to the prepared and approved project documentation; preparation of as-built and operational documentation; obtaining the occupancy permit; commissioning of facilities and handover of the operational subject of the contract; provision of warranty and guarantee services. Detailed information is contained in the Functional-Utility Program (PFU) Volume III of the SWZ.

PKP Polskie Linie Kolejowe S.A.

·Warszawa
Deadline:July 31, 2026

Construction supervision for design and execution of works on railway line 68, Stalowa Wola Rozwadów – Przeworsk, including author's supervision

Construction supervision for the design and execution of works on railway line No. 68 on the section Stalowa Wola Rozwadów – Przeworsk, including author's supervision within the project "Works on railway line No. 68 on the section Stalowa Wola Rozwadów – Przeworsk – Phase I". The scope of services also includes works covered by a time-limited option right as per § 7a of the contract, to the extent that the contracting authority exercises this option right.

PKP Polskie Linie Kolejowe S.A.

·Warszawa
Deadline:August 24, 2026
PLN 901,275

Tree and shrub felling for ISE Rybnik in 2026

Tree and shrub felling: Execution of works in the operational area of the Rybnik Exploitation Section along railway lines No. 140, 149, 157, 158, 159, 169, 173, 689, 957, 958, and 959 in 2026; detailed description in the tender documents (OPZ).

PKP Polskie Linie Kolejowe S.A. Zakład Linii Kolejowych w Tarnowskich Górach

·Tarnowskie Góry
Deadline:August 19, 2026

Find matching tenders automatically

With Patterno-HIT, receive relevant tenders daily, automatically filtered to your company profile.

Book Demo Now