Pipeline Route Construction: Primstal High Reservoir to Filtration Building
Construction of a new drinking water transport pipeline between the Primstal High Reservoir and the Filtration Building: approximately 1,800 m of ductile cast iron drinking water pipeline DN 250 to DN 300, including earthworks and civil engineering, trench shoring, dewatering, and restoration of affected surfaces. Additionally, renewal and rehabilitation of existing sewage channels, including approximately 540 m of trenchless sewer rehabilitation using hose lining in nominal diameters DN 200 to DN 400. Furthermore, approximately 1,900 m of micro-duct assembly for future fiber optic installation and protective pipe works for energis Netzgesellschaft, including approximately 1,500 m of protective pipes DN 110. Required testing, connection, and restoration works, as well as services for 113 identified interference points, are also included.
Gemeindewasserwerke Nonnweiler
·Nonnweiler